TenneT Holding B.V. (TenneT), owned by the Ministry of Finance of The State of the Netherlands, is an electricity transmission system operator. The company offers electricity transmission and system services. It constructs and maintains high voltage grid to transmit electricity from the producers to the regional grids, which distribute electricity to the end consumers. It also offers system services to maintain the balance between the supply and demand of electricity. The company through its subsidiaries offers services in the Netherlands and Germany. TenneT is headquartered in Arnhem, the Netherlands.

TenneT Holding B.V. - Power - Deals and Alliances Profile provides you comprehensive data and trend analysis of the company's Mergers and Acquisitions (M&As), partnerships and financings. The report provides detailed information on Mergers and Acquisitions, Equity/Debt Offerings, Private Equity, Venture Financing and Partnership transactions recorded by the company over a five year period. The report offers detailed comparative data on the number of deals and their value categorized into deal types, sub-sector and regions.

GlobalData derived the data presented in this report from proprietary in-house Power eTrack deals database, and primary and secondary research.

Scope

- Financial Deals - Analysis of the company's financial deals including Mergers and Acquisitions, Equity/Debt Offerings, Private Equity, Venture Financing and Partnerships.
- Deals by Year - Chart and table displaying information encompassing the number of deals and value reported by the company by year, for a five year period.
- Deals by Type - Chart and table depicting information including the number of deals and value reported by the company by type such as Mergers and Acquisitions, Equity/Debt Offering etc.
- Deals by Region - Chart and table presenting information on the number of deals and value reported by the company by region, which includes North America, Europe, Asia Pacific, the Middle East and Africa and South and Central America.
- Deals by Sub-sector - Chart and table showing information on the number of deals and value reported by the company, by sub-sector.
- Major Deals - Information on the company's major financial deals. Each such deal has a brief summary, deal type, deal rationale; and deal financials and target Company's (major public companies) key financial metrics and ratios.
- Business Description - A brief description of the company's operations.
- Key Employees - A list of the key executives of the company.
- Important Locations and Subsidiaries - A list and contact details of key centers of operation and subsidiaries of the company.
- Key Competitors - A list of the key competitors of the company.
- Key Recent Developments - A brief on recent news about the company.

Reasons to Buy

Get detailed information on the company's financial deals that enable you to understand the company's expansion/divestiture and fund requirements
- The profile enables you to analyze the company's financial deals by region, by year, by business segments and by type, for a five year period.

Understand the company's business segments' expansion / divestiture strategy
- The profile presents deals from the company's core business segments' perspective to help you understand its corporate strategy.

Access elaborate information on the company's recent financial deals that enable you to understand the key deals which have shaped the company
- Detailed information on major recent deals includes a summary of each deal, deal type, deal rationale, deal financials and Target Company's key financial metrics and ratios.

Equip yourself with detailed information about the company's operations to identify potential customers and suppliers.
- The profile analyzes the company's business structure, locations and subsidiaries, key executives and key competitors.

Stay up-to-date on the major developments affecting the company
- Recent developments concerning the company presented in the profile help you track important events.

Gain key insights into the company for academic or business research
- Key elements such as break up of deals into categories and information on detailed major deals are incorporated into the profile to assist your academic or business research needs.

Note*: Some sections may be missing if data is unavailable for the company.

Table of Contents
Table of Contents 2
List of Tables 5
List of Figures 6
TenneT Holding B.V., Power, Deals By Year, 2010 to YTD 2016 7
TenneT Holding B.V., Power Deals By Type, 2010 to YTD 2016 8
TenneT Holding B.V., Power, Deals By Region, 2010 to YTD 2016 9
TenneT Holding B.V., Power, Deals By Sector, 2010 to YTD 2016 10
TenneT Holding B.V., Power, Deals Summary, 2010 to YTD 2016 11
TenneT Holding B.V., Power, Deal Details 13
Asset Purchase 13
EON Sells Its High Voltage Transmission Network To TenneT 13
TenneT Acquires Electricity Grid in Utrecht Province, Netherlands from Stedin 13
Partnerships 14
Statnett To Form Partnershiop With TenneT TSO And KfW For Interconnector System Project Between Germany And Norway 14
Debt Offering 15
TenneT Prices Public Offering of 1.25% Bonds Due 2033 for USD559.8 Million 15
TenneT Raises USD567.6 Million in Public Offering of 1% Bonds Due 2026 16
TenneT Raises USD567.6 Million in Public Offering of 1.875% Bonds Due 2036 17
TenneT Raises USD87.8 Million in Private Placement of 0.646% Bonds Due 2022 17
TenneT Raises USD114 Million in Private Placement of 0.989% Bonds Due 2024 18
TenneT Raises USD62.3 Million in Private Placement of 1.31% Bonds Due 2026 19
TenneT Raises USD57 Million in Private Placement of 1.5% Bonds Due 2028 20
TenneT Raises USD157.3 Million in Private Placement of 1.75% Bonds Due 2031 21
TenneT Raises USD91.2 Million in Private Placement of 2% Bonds Due 2036 22
TenneT Raises USD560.2 Million in Public Offering of 0.875% Bonds Due 2021 22
TenneT Raises USD560.2 Million in Public Offering of 1.75% Bonds Due 2027 23
TenneT Holding Completes Private Placement Of 3.25% Senior Bonds For US$694.62 Million 25
Acquisition 25
Allianz And Munich Re Plan To Invest In Power Grid Operator, TenneT TSO 25
TenneT Holding B.V. - Key Competitors 27
Key Employees 28
Locations And Subsidiaries 29
Head Office 29
Other Locations & Subsidiaries 29
Recent Developments 31
Dec 13, 2016: TenneT connects offshore wind farm Veja Mate to grid connection Borwin2 31
Nov 08, 2016: VBMS awarded Borssele Alpha export cabling contract 32
Oct 06, 2016: Mega Transport of heavy transformer on A2 to Breukelen 33
Oct 05, 2016: Invitation for the supply of Control Power (aFRR) for the first quarter of 2017 34
Sep 16, 2016: Ground-breaking ceremony and symbolic cable pulling for NordLink – important building block of the energy transition 35
Aug 24, 2016: DolWin3 is clear: SeaTerra completes investigation of 278 objects and removal of 8 ordnance targets from the DolWin3 cable route. 36
Aug 22, 2016: TenneT awards North Sea Offshore Wind Farm export cable monitoring project to LIOS 37
Aug 01, 2016: TenneT prepares grid system for renewable energy growth 38
Aug 01, 2016: Launch of the new Belgian-French & Belgian-Dutch Intraday solution 40
Jul 29, 2016: TenneT’s half-year figures show good progress and continued high security of supply 41
Jul 25, 2016: Pylon TenneT is 6 meters higher: TenneT Holding 43
Jul 19, 2016: Connecting additional offshore wind farm of 700 MW by 2023 feasible 44
Jul 19, 2016: MMT signs four year framework agreement with TenneT 45
Jul 15, 2016: ACM certifies TenneT as operator of the offshore grid 46
Jul 06, 2016: Growth of solar and wind power and reliability of electricity principles for investments TenneT in the Netherlands 47
Jun 30, 2016: Additional research into major power outage in 2015 completed: TenneT 49
Jun 21, 2016: Offshore grid connection DolWin2 taken from the power to perform repair work 50
Jun 20, 2016: TenneT starts expansion of the Meeden-Diele interconnector between the Netherlands and Germany 51
Jun 16, 2016: Closer North Sea cooperation on sustainable energy 52
Jun 10, 2016: TenneT presents Hub and Spoke concept for large scale wind energy on the North Sea 53
Jun 09, 2016: TenneT begins fieldwork for cable routes of offshore wind farms off Dutch Coast 56
Jun 02, 2016: TenneT opens information center for Doetinchem-Wesel 380 kV project 57
May 23, 2016: TenneT and Nuon to realize black start facility in Netherlands 58
May 19, 2016: TenneT publishes first Quality and Capacity Document for the offshore grid 59
May 14, 2016: Support structure for offshore transformer platform DolWin disembarked gamma: TenneT 60
May 12, 2016: TenneT boosts power pylons three meters up 61
May 09, 2016: Green light for construction COBRA cable 62
May 04, 2016: TenneT laid submarine cables for the offshore grid connection project Nordergrunde 63
Apr 07, 2016: Market prices of electricity in the Netherlands fall further: TenneT Holding 64
Apr 01, 2016: SPIE and Dura Vermeer will build a 380 kV interconnection 65
Mar 21, 2016: TenneT transmits 7.4 terawatt hours of wind energy from the North Sea on land - Result 2015 compared to the previous year almost sixfold 66
Mar 09, 2016: TenneT Selection - High Voltage Secondary Systems "Wind op Zee" 67
Mar 08, 2016: Investments TenneT for tomorrow's onshore and offshore electricity grid reach all-time high 68
Mar 08, 2016: TenneT select Enschede world first with 'icy' super cable 69
Mar 08, 2016: DolWin3 achieved further progress of the project in the supply of around one million German households with clean energy 70
Feb 26, 2016: Obligation for continued operation of the power plant Irsching 4 must be accompanied by appropriate compensation 71
Feb 11, 2016: SMA collaborates with Tennet for better solar power feed in predictions 72
Feb 02, 2016: TenneT opens cable storage facility at Eemshaven 73
Jan 29, 2016: Petrofac contract for Heerema Fabrication Group 74
Jan 29, 2016: New legislative proposal for windmill parks at sea to be submitted in February 2016 75
Jan 26, 2016: New cost-efficient power cable represents world first for TenneT 76
Dec 23, 2015: Dutch offshore wind power tenders face further delay 77
Dec 03, 2015: TenneT signs agreements for power transformers and GIS for Dutch offshore platforms 78
Dec 02, 2015: Outcomes research capabilities of wiring known: TenneT 79
Nov 09, 2015: Dutch Renewable Energy Federation established 80
Nov 02, 2015: Omroep Zeeland aboard with cable survey Borssele 81
Oct 22, 2015: TenneT launch environmental impact assessment for connecting wind farms Dutch Coast South 82
Oct 12, 2015: TenneT investigates bottom Westerschelde for connecting wind farms 83
Oct 05, 2015: TenneT wants to spend 130 million euros to reduce transmission tariffs for electricity 84
Sep 29, 2015: Cross-border ‘electricity highways’ and domestic production capacity ensure sufficient supply of electricity in the Netherlands 85
Sep 18, 2015: TenneT start tender process for selecting offshore substations and marine cables 87
Sep 10, 2015: TenneT to undertake demonstration project for innovative ‘super cable’ 88
Aug 10, 2015: ABB installs world's most powerful offshore converter platform in the North Sea 89
Jul 30, 2015: TenneT makes large grid investments to secure electricity supply while realising solid half-yearly results 90
Jul 29, 2015: Atlas Professionals Secures German North Sea Project with TenneT 92
Jul 28, 2015: ABB hands over Germany’s DolWin1 offshore wind energy link 93
Jul 28, 2015: DolWin1 completed: TenneT brings its fifth offshore grid connection into operation this year 94
Jul 20, 2015: Invitation for the market consultation regarding the supply of a black-start facility in the south of the Netherlands 95
Jul 17, 2015: Alstom and TenneT to reach another important milestone in the offshore DolWin3 project 96
Jun 22, 2015: Successful commissioning of HelWin2 HVDC grid connection: Prysmian Group 97
May 20, 2015: Energy consumption, production, imports and exports April 2015 98
Apr 09, 2015: New step in linking European electricity markets 99
Mar 26, 2015: Laetitia Griffith to join TenneT Supervisory Board 100
Mar 19, 2015: ABB wins $900 million order to connect Norwegian and German power grids 101
Mar 18, 2015: Energy consumption, production, imports and exports February 2015 102
Mar 13, 2015: TenneT invests in security of supply and energy transition 103
Mar 09, 2015: TenneT starts online stakeholder consultation process for offshore electricity grid 105
Feb 10, 2015: Green light for important electricity connection between Norway and Germany 106
Feb 09, 2015: Siemens hands over HelWin1, the second North Sea grid connection to TenneT 107
Appendix 108
Methodology 108
About GlobalData 108
Contact Us 108
Disclaimer 108

List of Tables
TenneT Holding B.V., Power, Key Facts, 2015 1
TenneT Holding B.V., Power, Deals Summary, 2010 to YTD 2016 1
TenneT Holding B.V., Power, Deals By Year, 2010 to YTD 2016 7
TenneT Holding B.V., Power Deals By Type, 2010 to YTD 2016 8
TenneT Holding B.V., Power, Deals By Region, 2010 to YTD 2016 9
TenneT Holding B.V., Deals By Sector, 2010 to YTD 2016 10
TenneT Holding B.V., Power, Deals Summary, 2010 to YTD 2016 11
EON Sells Its High Voltage Transmission Network To TenneT 13
TenneT Acquires Electricity Grid in Utrecht Province, Netherlands from Stedin 13
Statnett To Form Partnershiop With TenneT TSO And KfW For Interconnector System Project Between Germany And Norway 14
TenneT Prices Public Offering of 1.25% Bonds Due 2033 for USD559.8 Million 15
TenneT Raises USD567.6 Million in Public Offering of 1% Bonds Due 2026 16
TenneT Raises USD567.6 Million in Public Offering of 1.875% Bonds Due 2036 17
TenneT Raises USD87.8 Million in Private Placement of 0.646% Bonds Due 2022 17
TenneT Raises USD114 Million in Private Placement of 0.989% Bonds Due 2024 18
TenneT Raises USD62.3 Million in Private Placement of 1.31% Bonds Due 2026 19
TenneT Raises USD57 Million in Private Placement of 1.5% Bonds Due 2028 20
TenneT Raises USD157.3 Million in Private Placement of 1.75% Bonds Due 2031 21
TenneT Raises USD91.2 Million in Private Placement of 2% Bonds Due 2036 22
TenneT Raises USD560.2 Million in Public Offering of 0.875% Bonds Due 2021 22
TenneT Raises USD560.2 Million in Public Offering of 1.75% Bonds Due 2027 23
TenneT Holding Completes Private Placement Of 3.25% Senior Bonds For US$694.62 Million 25
Allianz And Munich Re Plan To Invest In Power Grid Operator, TenneT TSO 25
TenneT Holding B.V., Key Competitors 27
TenneT Holding B.V., Key Employees 28
TenneT Holding B.V., Other Locations 29
TenneT Holding B.V., Subsidiaries 29

List of Figures
TenneT Holding B.V., Power, Deals by Type, 2010 to YTD 2016 1
TenneT Holding B.V., Power, Deals By Year, 2010 to YTD 2016 1
TenneT Holding B.V., Power, Deals By Region, 2010 to YTD 2016 1
TenneT Holding B.V., Power, Deals By Sector, 2010 to YTD 2016 1
TenneT Holding B.V., Power, Deals By Year, 2010 to YTD 2016 7
TenneT Holding B.V., Power, Deals by Type, 2010 to YTD 2016 8
TenneT Holding B.V., Power, Deals By Region, 2010 to YTD 2016 9
TenneT Holding B.V., Power, Deals by Sector, 2010 to YTD 2016 10


If the above report does not have the information suitable for your business, we can provide custom research that can be lucrative for your business or enhance your profession.